Can anyone give a flavor of how orders get placed with semiconductor manufacturers?
I was originally under the impression that if Company XYZ wants to order 100,000 chips per month from Megalogic Inc, they contact Megalogic and tell them, "I need 100,000 chips as soon as you can" and Megalogic says OK, we can supply them in 8 weeks at this price, and then XYZ places an order.
But I'm guessing that it's more complicated, and there might be an order placed ahead of time for delivery in, say, 20 weeks, even though the minimum lead time might be 8 weeks...
How far in advance do large companies place an order? (Under normal conditions, never mind the crazy 52-week lead times in the last couple of years.)
I was originally under the impression that if Company XYZ wants to order 100,000 chips per month from Megalogic Inc, they contact Megalogic and tell them, "I need 100,000 chips as soon as you can" and Megalogic says OK, we can supply them in 8 weeks at this price, and then XYZ places an order.
But I'm guessing that it's more complicated, and there might be an order placed ahead of time for delivery in, say, 20 weeks, even though the minimum lead time might be 8 weeks...
How far in advance do large companies place an order? (Under normal conditions, never mind the crazy 52-week lead times in the last couple of years.)